Streatham Ice Skating Action Group

Campaign News

Home

Aims and Objectives

Members

Campaign News

Project Updates

Rink History

Rink Events

Links

Contact SISAG

See below for news on:

Revised plans get planning consent (added 20.11.08)

Tesco exhibition for residents (updated.19.10.08)

Revisions to plan mean shorter development time (updated 05.10.08)

6 month feasibility study complete (added 14.06.08)

6 month feasibility study complete (added 14.06.08)

Streatham medallists at British Championships Jan 2008 (added 15.01.08)

Section 106 and Development Agreement signed (updated 18.12.07)

Section 106 and Development Agreement agreed (updated 08.11.07)

Hub update at Council meeting 4th July 2007 (updated 22.07.07)

SPAM emails from SISAG domain (added 25.05.07)

Public meetings for Leisure Centre users 8th May 2007 (updated 13.05.07)

For older news see Campaign News - Archive X

Revised plans get consent

The revised plans, including the temporary bus garage, gained planning consent at a meeting of the Planning Applications Committee on 11th November 2008. To see the officers' report and minutes of the meeting go to

http://www.lambeth.gov.uk/Services/CouncilDemocracy

Click on 'Calendar of meetings' on the right hand side. Fnnd 11th November. Click on the link for 'Planning Applications Committee 1 11/11'

Back to Top of Page

Tesco exhibition for residents

In connection with the revised planning application, Tesco held an exhibiton to offer residents living in adjacent roads an update on the changes to the Streatham Hub proposals on 4th October 2008. The display boards from the exhibition are here (3.9Mb - opens in new window)

Tesco display boards Oct 2008

Tesco believes that nearby residents, particularly those in Natal Road and Ellora Road, will benefit from changes to access and design.

Back to Top of Page

Revisions to plan mean shorter development time

An update from the "Future Streatham" team at Lambeth on 19th September 2008 says:

Plans to transform leisure facilities in Streatham have taken another step closer. The developer, Tesco, has submitted revisions to the original planning application of 2005 that will mean the whole scheme, including new housing, could be complete a year earlier than planned.

Revised plans include the proposal to provide a temporary bus garage. This means the swimming pool will need to close for less time than previously thought, while the new leisure centre could open slightly earlier than planned. Estimates suggest the swimming pool would close in Autumn 2010 and the new leisure centre could open Summer 2011. The existing ice rink will remain open until the new ice rink is ready to use.

The announcement of the revised planning application was in the South London Press on 26th September. The main reference for the new planning application is 08/03477/FUL. The description is:

1) Variation of conditions attached to planning permission ref 02/02557/FUL for the redevelopment of the site to provide a leisure complex (ice rink, swimming pool, health and fitness facilities and community uses), 250 residential units, including affordable housing, a retail store, bus lay-over, public square together with associated car parking and servicing. 08/03477/FUL

2) Temporary change of use for a period of 4 years to bus stand facility and associated and ancillary development including welfare and mess room. Construction of retaining walls at boundaries and creation of hard standing in all other areas. Proposal also requires the demolition of the former Sunday school. 08/03455/FUL

3) Demolition of existing buildings on site, including the ice rink and swimming pool buildings to allow redevelopment of the site to include leisure, retail and residential uses. 08/3457/CON

Demolition of former Sunday School building attached to United Reform Church, to allow redevelopment of the site to include leisure, retail and residential uses. 08/03454/LB

A document giving an overview of the application is here.

The details can be viewed at the Planning Advice Centre, Phoenix House, 10 Wandsworth Road, SW8 2LL weekdays from 9.30 am to 4.40 pm for 21 days from the publication of the notice (i.e. until Friday 17th October) or at Streatham Tate Library during normal opening hours. Written comments should be made within this period to the Director of Planning at the same Phoenix House address.

The application (and facility for comments) is also available online at the Lambeth Public Access for Planning Database

To see the application

1. Click on "Application Search" on the left. A form is displayed.

2. Enter the reference 08/03477/FUL in the Application Reference field.

3. Click the "Search" button at the bottom.

4. When the application is displayed, click the "Click to View" arrow on the right.

5. The information is displayed under several tabs. The documents are available on the "Associated Documents" tab.

At the top there is a button "Submit comments ..." which leads to another form to submit comments.

Back to Top of Page

6 month feasibility study complete

After the signing of the Section 106 and Devlepment Agreement by Lambeth Council and Tesco on 7th December 2007 there was a six-month period for a feasibility study. This has now finished and the scheme moves on to the next stage, in which Tesco will invite contractors to tender for the scheme. Building could start in early 2009, though workers will be on site earlier carrying out preliminary work.

Lambeth's official press release is here

Back to Top of Page

Streatham medallists at British Championships 2008

At the British Ice Figure and Synchro Skating Championships in Sheffield, Streatham ice dancers Phillipa Towler-Green and Phillip Poole won silver medals in the Senior Ice Dance category.

Pippa and Phillip now go on to compete for Britain alongside Sinead and John Kerr at next week's European Championships in Zagreb, Croatia. This event will be televised on Eurosport (22nd-27th Jan). We are not sure yet if there will be any terrestrial TV coverage.

In the younger age range, Melissa Chan and Tobias Wallis also won silver medals in the Novice Ice Dance category.

Congratulations to the Streatham skaters.

Back to Top of Page

Section 106 and Development Agreement signed

Lambeth Planning department have confirmed that the Section 106 and Development agreement were signed on 7th December 2007 and the planning permission issued. Now the contract has been signed a contractor can be selected and work can begin.

As reported in the South London Press (14th December) Cabinet member for regeneration and enterprise councillor Paul McGlone said: "As with any complex project, there is still some way to go before things start happening on the ground. But progress is being made and we continue to pass major milestones on our way to completing this project."

One of the reasons this is a major milestone is because the Section 106 is the document containing the clauses guaranteeing continuity of ice skating provision.

Lambeth's official press release is here

Back to Top of Page

Section 106 and Development Agreement exchanged

The Section 106 and Development agreement were agreed by Lambeth Council and Tesco on 11th October 2007. The agreements are not yet "sealed". It is hoped that both this step and the issuing of planning permission will occur during November 2007

The information about the documents being agreed is contained in a written answer to a question to the full Council meeting on 7th November 2007. The relevant question and answer are below. The pdf document containing the written answer is here

Council questions Nov 2007

or to find all the papers for the meeting go to

http://www.lambeth.gov.uk/Services/CouncilDemocracy/

Follow the link to 'Calendar of meetings' on the rhs, then scroll to 11th November for the Council meeting and click on the link.

By: Councillor Dave Malley (17.10.07)

To: Councillor Paul McGlone, Cabinet Member for Regeneration and Enterprise

Streatham Hub

Can you advise what action you have taken to ensure that the Streatham hub ice rink and swimming pool development is successfully delivered within a reasonable timeframe

Party: Labour

Answer:

Whilst responsibility for the Streatham Hub Scheme delivery rests with Tesco, the Council retains the right to closely monitor the scheme. As a result, the scheme’s contract will be actively managed by the Physical Regeneration Team, which will report to the Future Lambeth Programme Board on a monthly basis as well as oversight by the relevant Cabinet members. The Physical Regeneration Team is currently mobilising a team for this project and together with Leisure Services is currently working with Tesco to progress the final stages of design development of the leisure centre and ice rink.

By way of background, on 11th October 2007, Tesco and the Council agreed the Section 106 and the Development Agreement. The Section 106 defines the benefit to be derived from the Streatham Hub scheme, whereas the Development Agreement defines how and when the benefits will be delivered. The two documents sit alongside each other.

Once planning permission has been granted, the Development Agreement’s commencement is triggered. From this date there is up to 12 months of activities before we will see works on site. The developer has six months within which it can determine the agreement (i.e. to proceed or not). This six month period is referred to as the feasibility review period, and allows Tesco to review the scheme’s design and costs and finalise all outstanding land issues. Following the six month period, there is a further 30 week period before an “unconditional date” is reached. This period is to allow final tenders to be reviewed and for the final development costs to be determined. Both the Council and Tesco can determine the scheme by the unconditional date. The Council could decide to not proceed with the development with no liability for abortive costs.

The construction period, capped at 130 weeks, commences on the “unconditional date”. The order of development is clearly outlined in the Development Agreement as follows:

  • New bus terminal (to be completed within 18 months of the unconditional date)
  • Phase 1 Ice & Leisure Centre (this stage could be combined with the building of the bus terminal)
  • Phase 2 Ice & Leisure Centre / preparation works for underground car parks and foundations.
  • Phase 1 Housing ( rear of the site) / Public Square
  • Store and Phase 2 Housing.

Clearer dates cannot be provided until the planning permission is issued, as the date of issue sets the base date, but following planning permission, the completion of the scheme will be no longer than 187 weeks (Up to 57 for feasibility review and determination of final development costs and up to 130 for construction). If approval is issued shortly, as hoped, and the scheme progresses to plan then the Leisure Centre will open in 2010, 12 months before the overall scheme completion.

Back to Top of Page

Hub update at Council meeting 4th July 2007

Councillor Julian Heather put down a question asking for an update on the Streatham Hub development to the full Council meeting on 4th July 2007. A written answer was published in the week before the meeting. The relevant question and answer are below. In reply to a supplementary question at the meeting, the Council's commitment to continuity of skating was reconfirmed. The pdf document containing the written answer is here

Council questions July 2007

and the supplementary question and answer are contained in

Council minutes July 2007

or to find all the papers for the meeting go to

http://www.lambeth.gov.uk/Services/CouncilDemocracy/

Follow the link to 'Calendar of meetings' on the rhs, then scroll to 4th July for the Council meeting and click on the link.

By: Councillor Julian Heather (13.06.07)

To: Councillor Paul McGlone, Cabinet Member for Regeneration and Enterprise

Streatham Hub Progress Report

In the light of the abolition of the Streatham Area Committee, which received updates at each meeting of progress on the Streatham Hub Development, would the Cabinet Member for regeneration provide an update on what progress has been made since the last Streatham Area Committee held on 25th April on taking forward the Streatham Hub development and give an indication of the key delivery timescales

Party: Liberal Democrat

Answer:

The technical review of the complete Streatham Hub Scheme has been completed and the guide price for the overall development reduced to a level acceptable to Tesco.

The first 3 months of the planned ‘review period’ in the scheme has been complete. This represents the period during which Tesco could have unilaterally withdrawn because the scheme couldn’t be made to be ‘financially’ viable.

The feasibility of the scheme has been tested and reviewed during this period. As a consequence the phasing of the various buildings and the exchange of property has had to be altered. Subsequently we have had to bring the Section 106 and the Development Agreement in line with the revised building schedule.

This has been completed however we are awaiting a ‘letter of assurance’ from Tesco regarding the critical path in the building programme before the Executive Directors can reasonably sign off the Delegated Decision and the documents can be exchanged.

On the 15th of June the 6 month development and procurement phase of the project began regardless of the exchange of documents. The first meeting of the Technical Review Group concerning the Leisure Centre will take place on the afternoon of the 21st of June.

A new team of Canadian engineers expert in Ice Arenas - is now involved and the Project Team have completed a series of visits to sites in the UK . This in order to ensure a greatly increased awareness of the issues associated with:

  • the initial building.
  • the long term life cycle.
  • the impact of the facility layout on management performance and costs.
  • energy use.

If there are revisions to the floor layouts these will be tested upon the Streatham Stakeholders Technical Group and the Council’s new Leisure Contractor Greenwich Leisure Ltd.

Other than for the exchange of documents all other factors are progressing according to the revised critical path for the project that was included in the last report to the Area Committee.

Supplementary Question

Can assurance be given that there will be continuity of skating while the new centre is being built and before it opens?

Supplementary Answer

This was a cross-party supported scheme. It had been made clear to Tesco that certain elements were non-negotiable and the continuity of skating was one of these. Once the commercial sensitivities were concluded full information would be given to local stakeholders, councillors and the public. Streatham was considered to be a key part of this borough.

Back to Top of Page

SPAM emails from SISAG domain

Starting on 23rd May 2007 some spam emails were sent from fictitious addresses appearing to come from the sisag.org.uk domain. If you are looking at this website because you have received such an email please delete it. We apologise for the inconvenience but this is beyond our control - it is unfortunately easy for people to 'fake' from-addresses on emails. SISAG only sends out solicited emails about Streatham Ice Rink and the Streatham Hub development.

Back to Top of Page

Public meetings for Leisure Centre users 8th May 2007

Two public meetings organised by Lambeth Council and Greenwich Leisure Ltd (GLL) for users of the existing Streatham Leisure Centre were held on Tuesday 8th May 2007. Lambeth's announcement is here

Back to Top of Page

For older news see Campaign News - Archive X

Page last updated: 20th November 2008